설치시공

Renewable Energy

Installation

Solar power business concept

Department selection criteria

Review geographical conditions
  • Whether to gain access to solar power plant construction sites
    (Minimum 4m)
    → Difficulty in carrying out business if there is no access road
  • Determine how far left, right, and front shadow effects can be.
  • Check the occurrence of civil engineering costs such as landfilling and soil cutting.
  • How far is KEPCO Samseong Jeonju from the business site.
  • Check how much solar power capacity is available.
  • Ensure that power generation business permits are available.
    (Confirmation of KEPCO grid connection)
  • Confirmation of official site of site (rice field, field)
  • Determine if development activity is possible
    (Agricultural promotion area, military facility protection area, cultural property protection area)
Neighboring area
  • Distance from site to town boundary
    (See the Local Authority Ordinance)
  • Distance to facilities such as housing (see local municipal ordinance)
  • Confirmation of complaints around business premises before purchase
  • Confirmation of development activity permission (Guideline for permission to operate, permission for development activity permission)
  • Prohibition of development activities in the contact area
    (Highway [10m], general highway [5m], local road [5m])

Required documents

Electricity Business License Application Form Apply for PPA Report construction plan
  • Electric business
  • Application for permission (1 copy)
  • Power transmission relationship view
  • Module layout,
  • Side view
  • Land use plan
  • Confirmation circle
  • Cadastral map, land register
  • Certified copy of registration
  • Building Management Director
    (For buildings)
  • Loan agreement
  • Use consent
  • Identity verification agreement
  • ID card
  • Family Relations Certificate
  • warrant
  • Used seal
  • Certificate of seal
  • PPA Application
  • Bank Transfer
  • Transaction Agreement
  • Electricity application form
  • business plan
    (Licensing documents)
  • Power Generation License
  • Business Registration
  • A copy of passbook
  • Certificate of seal
  • Drawing
    (Single wire connection diagram, system diagram)
  • Module certificate
  • Module test report
  • Inverter test report
  • Contractor
  • Certificate of seal
  • Contractor
  • Electrical Construction Certificate
  • Construction plan
  • Declaration of Technical Specifications
  • Inverter Specifications
  • Module Specifications
  • Supervision Placement Confirmation
  • Power Generation License
  • Construction plan report drawing
  • Structural safety review
    (Building facility facilities)
Application form before use Business start notification form Equipment confirmation
  • Application form before use
  • Power Generation License
  • Module layout, side view
  • Notification of Repair Plan Notification
  • Inspection Placement Confirmation
  • Certificate of elected electric safety manager
  • Inverter self test report
  • Module self test report
  • Module layout (actual installed layout)
  • Module certificate
  • Module test report
  • Inverter test report
  • Construction plan report drawing
    (Single wire connection diagram, system diagram)
  • Application (foreground, module, inverter photo)
  • Power Generation License
  • Business Registration
  • Electric Safety Manager
  • Certificate of seniority report
  • Inverter self test report
  • Module self test report
  • Pre-use test certificate
  • Supply contract
  • Business Registration
  • Power Generation License
  • Pre-use test certificate
  • Estimate
  • Installation pictures
  • Single wire connection diagram
  • Information providing agreement
  • Confirmation Ratio
  • KEPCO Contract No. Commercial Operation
  • Start Date
  • Module certificate
  • Inverter test report
  • Status map of buildings
  • Land register, cadastral map
  • Installation drawing
  • Structural safety review
    (Building facility facilities)

Step

Plan for facility construction

Facility overview

Installation type: Fixed slope type installed on general land

Installation type: Slope fixing type installed on the upper part of the building

※ This image is an image for reference purposes only.

Construction equipment details

Solar power system – 100kW
Installation Specification
(Design basis)
Solar cell module Hansol Technics / 300W modules total 300
Volume 100kW
Inverter SUNGROW / SG50KTL-M Series (2 units)
Structure Inclined fixed type (20°, Hot-dip galvanizing)
Monitoring SUNGROW Monitoring system
※ Depending on the equipment supply plan, it can be replaced with equivalent equipment or more.

※ This image is an image for reference purposes only.

Solar power business procedure

※ Notification of construction plan
If the approval of development activity review committee is rejected at the time of application for development activity, administrative litigation is proceeded after complaint filing.